A. PREPARATION FOR OPERATION
1. The supply voltage must match the dryer voltage as stated on the aluminum dryer data label which is
located in the right hand side of the main electrical enclosure.
2. Open
ALL steam supply lines and condensate return line shutoff valves.
3. A compressed air supply of 80 PSI (5.51 bar) must be connected into the dryer’s fitting located at the rear
corner of the lower heat console section.
4. The dryer exhaust duct must be vented to the outdoors.
5. The dryer must be lagged to the floor and leveled for proper operation.
6. A fresh air supply from the outdoors of 13,000 cfm (368 cmm) must be available to the dryer.
7. ALL service doors must be closed and ALL access panels and tilt guards must be installed on the dryer.